This method of test is intended for determining the relationship between the moisture content anddensity of soils when compacted in a given mold of a given size with a 4.54-kg (10-lb) rammerdropped from a height of 457 mm (18 in.). Four alternate procedures are provided as follows:
Method A-A 101.60-mm (4-in.) mold: Soil material passing a 4.75-mm (No. 4) sieveSections 4 and 5.
Method B-A 152.40-mm (6-in.) mold: Soil material passing a 4.75-mm (No. 4) sieveSections 6 and 7.
Method C-A 101.60-mm (4-in.) mold: Soil material passing a 19.0-mm (3/4-in.) sieveSections 8 and 9.
Method D-A 152.40-mm (6-in.) mold: Soil material passing a 19.0-mm (3/4-in.) sieveSections 10 and 11.
1.2. The method to be used should be indicated in the specifications for the material being tested. If nomethod is specified, the provisions of Method A shall govern.
1.3. This test method applies to soils mixtures that have 40 percent or less retained on the 4.75-mm(No. 4) sieve, when Method A or B is used and 30 percent or less retained on the 19.0-mm (0.75-in.)sieve, when Method C or D is used. The material retained on these sieves shall be defined asoversize particles (coarse particles).
1.4. If the test specimen contains oversize particles, and the test specimen used for field densitycompaction control, corrections must be made according to T 224 to compare the total fielddensity with the compacted specimen. The person or agency specifying this method shall specify aminimum percentage of oversize particles below which correction for oversize need not beapplied. If no minimum percentage is specified, correction shall be applied to samples with morethan 5 percent by mass of oversize particles.
1.5. If the specified oversized maximum tolerances are exceeded, other methods of compaction controlmust be used.
Note 1--One method for the design and control of the compaction of such soils is to use a test fillto determine the required degree of compaction and a method to obtain that compaction. Then usea method specification to control the compaction by specifying the type and size of compactionequipment, the lift thickness and the number of passes.
PDF

All of our standards document are available in PDF (Portable Document Format), an electronic, downloadable format.You will be able to download the file in your account downloads.

Multi-User Access

After purchasing, you have the ability to assign each license to a specific user.

Printable

At any time, you are permitted to make printed copies for your and your members' reference use.

AASHTO M 213-01 (2019)

AASHTO M 213-01 (2019)

Standard Specification for Preformed Expansion Joint Fillers for Concrete Paving and Structural Cons..

$27.00 $54.00

AASHTO R 26-01 (2013)

AASHTO R 26-01 (2013)

Standard Practice for Certifying Suppliers of Performance-Graded Asphalt Binders..

$39.00 $78.00

AASHTO R 27-01 (2015)

AASHTO R 27-01 (2015)

Standard Practice for Assessment of Corrosion of Steel Piling for Non-Marine Applications..

$45.00 $89.00

AASHTO SRA-3

AASHTO SRA-3

A Guide for the Development of Rest Areas on Major Arterials and Freeways, 3rd Edition..

$23.00 $45.00